The new Dallas Area Rapid Transit Silver Line is nearly three-quarters completed, which has yielded a visible sign of progress toward the promised east-west regional connections of the new train.
But the project is about 65% complete overall, according to DART, which has installed 120,120 linear feet of new railroad to go along with existing rail that will be part of the Silver Line.
A DART Silver Line train crosses a bridge nearing US-75 during segment testing of the new light rail line on Sunday, Aug. 25, 2024, in Richardson.(Smiley N. Pool / Staff Photographer) Beginning ...
Dallas Area Rapid Transit has begun end-to-end testing for the upcoming Silver Line. Trains will leave Plano and end at DFW ...
DART leaders are concerned what a potential reduction in funding could mean for the area's new Silver Line rail service. Dallas Area Rapid Transit officials say their plans for the anticipated ...
The agency is laying 26 miles of commuter rail called the Silver Line, at a cost of ... would create a lake if DART didn’t redo the drainage pipes and build a new pump station right behind ...
The building, at 15400 Knoll Trail Dr., is adjacent to Knoll Trail Station, a future DART commuter rail station ... on the Silver Line by late 2025 or early 2026. Testing on the new line between ...
$2B new train line could come online this year Major apartment developer eats up more DFW office space Major apartment developer eats up more DFW office space Public company quietly moves HQ to ...
Dallas Area Rapid Transit is receiving multiple train cars from Minnesota's Northstar line in order to boost inventory ahead ...